Residential Building No. 1
Section 1
Works are ongoing for the installation of external sewage networks.
Continued construction of vertical and horizontal elements (walls, columns, and slabs) on the 15th floor.
Section 2
Works are being carried out for the installation of external sewage networks.
Formwork is being installed for the subsequent pouring of vertical and horizontal elements (walls, columns, and slabs) on the 14th floor.
Section 3
Continued construction of vertical and horizontal elements (walls, columns, and slabs) on the 12th and 13th floors.
Vertical elements of the monolithic frame on the 12th floor are being installed.
Works are being carried out for the installation of external sewage networks.
Works are ongoing for the installation of external water supply systems.
Backfilling works are continuing.
In all sections, installation of ventilated channels and construction of staircases are being carried out.