11/2023
November 2023
Back
Works are being carried out for laying external sewerage networks, water supply, and a rainwater drainage system.
Installation of ventilation units is in progress.
Concrete casting for elevator shafts is underway.
Works on reinforcing and casting elements of the monolithic frame for the 19th floor are in progress.