Works are ongoing for the installation of external sewage networks, water supply, and rainwater drainage system.
Ventilation unit installation is in progress.
Concreting of elevator shafts is being carried out.
Reinforcement and concreting of elements of the monolithic frame for the 17th and 18th floors are in progress.